When is the best time to have project kickoff meetings?

Options
- At the beginning of the project
- When each deliverable is created
- At the start of each phase
- When the Communications Management plan is approved


CORRECT ANSWER : At the start of each phase

Discussion Board
Explanation-

Kick-off meetings take place at the beginning of the project and at the beginning of major phases, for larger projects. As new people join the team, they must be "kicked-off" into the project.